DC took stock of the Wak to Yomcha road.
Publish Date : 06/06/2025

Aalo the 5th June 2025: Ms Mamu Hage IAS Deputy Commissioner of West Siang District took stock of the road damages of Wak to Yomcha road. Some portion of the road has been blocked and later on it was cleared by executing agency. The landslides was occurred due to the recent heavy pour of the rain. Wak to Yomcha road is 26km long which the widening of the road is in progress. DC informed the executing agency not to compromise the quality of work and complete the road in time. It is also informed to the public of Taba Sora and Yomcha area not to travel in the night hours. DC along with the officers also visited Kodum to Bam trijunction road. Which is almost in the final stage.
DC also told the executing agency to keep the machineries on standby for any landslides during monsoon.
DC was accompanied by Sri Hento Riba CO Kodum, AE PWD and JE etc during the inspection.
DIPRO